Production Plan
Open MOs:48At Risk:21Late:6Rework Impact:5Actions Due Today:11
48 manufacturing orders
| Priority | Customer | MO Number | Part | Qty | Current Stage | Planned Start | Customer Required | System Forecast | Planner Committed | Variance | Primary Blocker | Action Owner | Planning Status | Planner Remark |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Bosch Power Tools | BPT-4471-02 Ejector Pin Holder | 240 | CNC Milling | 25 Jul | 12 Aug 2026 | 11 Aug 2026 | — | -1 days | None | — | On Track | — | ||
| Carsem Semiconductor | CSM-2210-A Lead Frame Punch | 120 | Awaiting Material | 25 Jul | 13 Aug 2026 | 13 Aug 2026 | — | 0 days | Purchasing | At Risk | — | |||
| Western Digital | WDC-8871 Base Plate Fixture | 60 | Wire EDM | 25 Jul | 14 Aug 2026 | 14 Aug 2026 | — | 0 days | None | — | On Track | — | ||
| Dyson Manufacturing | DYS-1120-C Impeller Core Insert | 80 | Heat Treatment (Sub-Con) | 24 Jul | 14 Aug 2026 | 14 Aug 2026 | — | 0 days | Sub-Con Coordinator | At Risk | — | |||
| Ansell Malaysia | ANS-3320 Former Mould Segment | 150 | Surface Grinding | 26 Jul | 17 Aug 2026 | 16 Aug 2026 | — | -1 days | None | — | On Track | Confirmed with production supervisor, recovery on night shift. | ||
| Flextronics Penang | FLX-6612-B Connector Cavity Block | 200 | Awaiting Material | 31 Jul | 18 Aug 2026 | 18 Aug 2026 | 18 Aug 2026 | 0 days | Purchasing | At Risk | Customer requested expedite. Material expected 14 Aug. Prioritise after MO-10481. | |||
| Osram Opto | OSR-9041 Lens Mould Core | 90 | Assembly | 30 Jul | 18 Aug 2026 | 18 Aug 2026 | — | 0 days | None | — | On Track | — | ||
| Kobe Precision | KBP-5510 Slide Retainer Plate | 45 | Final Inspection | 30 Jul | 19 Aug 2026 | 19 Aug 2026 | — | 0 days | Production | At Risk | — | |||
| Bosch Power Tools | BPT-4488-01 Gear Housing Jig | 30 | Awaiting Material | 29 Jul | 19 Aug 2026 | 19 Aug 2026 | — | 0 days | None | — | On Track | — | ||
| Carsem Semiconductor | CSM-2244-B Die Attach Nest | 300 | CNC Milling | 29 Jul | 20 Aug 2026 | 20 Aug 2026 | — | 0 days | QC | At Risk | — | |||
| Western Digital | WDC-8904 Actuator Locating Pin | 500 | CNC Turning | 02 Aug | 20 Aug 2026 | 20 Aug 2026 | — | 0 days | None | — | On Track | — | ||
| Dyson Manufacturing | DYS-1188-A Cyclone Shut-off Insert | 70 | Wire EDM | 02 Aug | 21 Aug 2026 | 21 Aug 2026 | — | 0 days | Purchasing | Blocked | — | |||
| Flextronics Penang | FLX-6640 Test Socket Base | 180 | Heat Treatment (Sub-Con) | 01 Aug | 21 Aug 2026 | 21 Aug 2026 | — | 0 days | None | — | On Track | — | ||
| Ansell Malaysia | ANS-3355 Dipping Line Bracket | 260 | Surface Grinding | 03 Aug | 24 Aug 2026 | 23 Aug 2026 | — | -1 days | None | — | On Track | Confirmed with production supervisor, recovery on night shift. | ||
| Osram Opto | OSR-9077 Reflector Cavity | 110 | Deburr | 02 Aug | 24 Aug 2026 | 24 Aug 2026 | — | 0 days | — | At Risk | — | |||
| Kobe Precision | KBP-5544 Spindle Adaptor Sleeve | 40 | Assembly | 07 Aug | 25 Aug 2026 | 25 Aug 2026 | — | 0 days | — | At Risk | — | |||
| Bosch Power Tools | BPT-4502-03 Armature Stack Fixture | 55 | Awaiting Material | 06 Aug | 25 Aug 2026 | 25 Aug 2026 | — | 0 days | Purchasing | At Risk | — | |||
| Carsem Semiconductor | CSM-2261 Wire Bond Clamp | 220 | Awaiting Material | 06 Aug | 26 Aug 2026 | 26 Aug 2026 | — | 0 days | None | — | On Track | — | ||
| Western Digital | WDC-8933-A Ramp Locating Block | 130 | CNC Milling | 05 Aug | 26 Aug 2026 | 26 Aug 2026 | 26 Aug 2026 | 0 days | Production | At Risk | — | |||
| Dyson Manufacturing | DYS-1201 Motor Bucket Core | 65 | CNC Turning | 05 Aug | 27 Aug 2026 | 27 Aug 2026 | — | 0 days | None | — | On Track | — | ||
| Flextronics Penang | FLX-6675-C Shield Can Punch | 400 | Wire EDM | 09 Aug | 27 Aug 2026 | 27 Aug 2026 | — | 0 days | — | At Risk | — | |||
| Ansell Malaysia | ANS-3390 Cuff Trim Blade | 175 | Heat Treatment (Sub-Con) | 09 Aug | 28 Aug 2026 | 28 Aug 2026 | — | 0 days | None | — | On Track | — | ||
| Osram Opto | OSR-9112-B LED Carrier Plate | 95 | Surface Grinding | 08 Aug | 28 Aug 2026 | 28 Aug 2026 | — | 0 days | Engineering | Blocked | Confirmed with production supervisor, recovery on night shift. | |||
| Kobe Precision | KBP-5571 Guide Bush Housing | 50 | Deburr | 10 Aug | 31 Aug 2026 | 30 Aug 2026 | — | -1 days | None | — | On Track | — | ||
| Bosch Power Tools | BPT-4519 Chuck Jaw Insert | 240 | Assembly | 09 Aug | 31 Aug 2026 | 31 Aug 2026 | — | 0 days | — | At Risk | — | |||
| Carsem Semiconductor | CSM-2285-A Mould Chase Plate | 85 | Final Inspection | 14 Aug | 01 Sept 2026 | 01 Sept 2026 | — | 0 days | None | — | On Track | — | ||
| Western Digital | WDC-8961 Head Stack Fixture | 140 | Awaiting Material | 14 Aug | 02 Sept 2026 | 02 Sept 2026 | — | 0 days | — | At Risk | — | |||
| Dyson Manufacturing | DYS-1233-B Filter Seal Mould | 75 | CNC Milling | 13 Aug | 02 Sept 2026 | 02 Sept 2026 | — | 0 days | None | — | On Track | — | ||
| Flextronics Penang | FLX-6702 Camera Bracket Jig | 210 | CNC Turning | 13 Aug | 03 Sept 2026 | 03 Sept 2026 | — | 0 days | — | At Risk | — | |||
| Osram Opto | OSR-9140 Diffuser Core Pin | 320 | Wire EDM | 13 Aug | 04 Sept 2026 | 04 Sept 2026 | — | 0 days | None | — | On Track | — | ||
| Kobe Precision | KBP-5599-A Bearing Locator Ring | 60 | Heat Treatment (Sub-Con) | 17 Aug | 04 Sept 2026 | 04 Sept 2026 | — | 0 days | — | At Risk | — | |||
| Ansell Malaysia | ANS-3421 Roller Support Shaft | 190 | Surface Grinding | 19 Aug | 07 Sept 2026 | 07 Sept 2026 | 07 Sept 2026 | 0 days | None | — | On Track | Confirmed with production supervisor, recovery on night shift. | ||
| Bosch Power Tools | BPT-4536-02 Rotor Trim Die | 100 | Deburr | 19 Aug | 08 Sept 2026 | 08 Sept 2026 | — | 0 days | None | — | On Track | — | ||
| Carsem Semiconductor | CSM-2303 Singulation Nest | 250 | Assembly | 19 Aug | 09 Sept 2026 | 09 Sept 2026 | — | 0 days | — | At Risk | — | |||
| Western Digital | WDC-8990-C Pivot Bore Gauge | 45 | Final Inspection | 19 Aug | 10 Sept 2026 | 10 Sept 2026 | — | 0 days | None | — | On Track | — | ||
| Dyson Manufacturing | DYS-1266 Brush Bar End Cap Mould | 80 | Awaiting Material | 24 Aug | 11 Sept 2026 | 11 Sept 2026 | — | 0 days | None | — | On Track | — | ||
| Flextronics Penang | FLX-6738-A PCB Support Pallet | 360 | Awaiting Material | 26 Aug | 14 Sept 2026 | 14 Sept 2026 | — | 0 days | — | At Risk | — | |||
| Osram Opto | OSR-9175 Heat Sink Fixture | 120 | CNC Turning | 26 Aug | 15 Sept 2026 | 15 Sept 2026 | — | 0 days | None | — | On Track | — | ||
| Kobe Precision | KBP-5620 Collet Forming Punch | 70 | Wire EDM | 26 Aug | 16 Sept 2026 | 16 Sept 2026 | — | 0 days | None | — | On Track | — | ||
| Ansell Malaysia | ANS-3455-B Glove Former Stand | 130 | Heat Treatment (Sub-Con) | 26 Aug | 17 Sept 2026 | 17 Sept 2026 | — | 0 days | — | At Risk | — | |||
| Flextronics Penang | FLX-6501 Housing Trim Die | 150 | Awaiting Material | 18 Jul | 05 Aug 2026 | 13 Aug 2026 | — | +8 days | Production | Late | Confirmed with production supervisor, recovery on night shift. | |||
| Carsem Semiconductor | CSM-2150-A Pick Head Nozzle Plate | 200 | Deburr | 18 Jul | 06 Aug 2026 | 14 Aug 2026 | — | +8 days | Production | Late | — | |||
| Western Digital | WDC-8790 Clamp Ring Fixture | 90 | Assembly | 17 Jul | 06 Aug 2026 | 17 Aug 2026 | — | +11 days | Planning | Late | — | |||
| Dyson Manufacturing | DYS-1050-C Shroud Core Insert | 60 | Final Inspection | 17 Jul | 07 Aug 2026 | 15 Aug 2026 | — | +8 days | Sub-Con Coordinator | Late | — | |||
| Bosch Power Tools | BPT-4390 Stator Lamination Die | 110 | Awaiting Material | 16 Jul | 07 Aug 2026 | 18 Aug 2026 | 18 Aug 2026 | +11 days | Purchasing | Blocked | — | |||
| Osram Opto | OSR-8960-A Optic Cavity Block | 85 | Awaiting Material | 23 Jul | 10 Aug 2026 | 19 Aug 2026 | — | +9 days | — | Late | — | |||
| Kobe Precision | KBP-5430 Feed Cam Plate | 40 | CNC Turning | 22 Jul | 10 Aug 2026 | 14 Aug 2026 | — | +4 days | Engineering | Blocked | — | |||
| Ansell Malaysia | ANS-3280-B Chain Guide Rail | 220 | Wire EDM | 22 Jul | 11 Aug 2026 | 20 Aug 2026 | — | +9 days | Planning | Late | — |