Rework
QC issue → affected MO → rework assigned → reinspection → closed → replanning impact.
| QC Issue Date | MO Number | Part | Affected Qty | Assigned To | Expected Completion | Rework Status | Reinspection | Planning Impact | Actual Closure | QC Issue |
|---|---|---|---|---|---|---|---|---|---|---|
| 08 Aug 2026 | CSM-2244-B Die Attach Nest | 24 | Deburr & Polish | 14 Aug 2026 | Pending | +2 days | — | Cavity depth 0.05mm below drawing on 24 pcs | ||
| 04 Aug 2026 | WDC-8790 Clamp Ring Fixture | 12 | Jig Grinding | 13 Aug 2026 | Pending | +5 days | — | Bore concentricity out of tolerance | ||
| 09 Aug 2026 | FLX-6640 Test Socket Base | 18 | CNC Turning | 16 Aug 2026 | Pending | +1 days | — | Thread pitch incorrect on 18 pcs |