Overview
Operational visibility for management. Click a figure to open the related production orders.
MO Status
- On Track21
- At Risk17
- Late6
- Blocked4
Main Causes of Delay
Delivery Risk — Next 4 Weeks
| Week 1 | 7 due | 5 at risk | |
| Week 2 | 9 due | 4 at risk | |
| Week 3 | 10 due | 6 at risk | |
| Week 4 | 8 due | 4 at risk |
Forecast Accuracy
Current month
2.8 days
Previous month
4.2 days
Improvement
33%
Average system forecast error
2.6 days
Average planner forecast error
3.1 days
Rework
Open rework cases
5
Average rework lead time
5.4 days
Rework affecting delivery
5
QC issue → rework start
1.2 days
Top Delivery Risks
| Customer | MO | Part | Customer Required | Forecast Completion | Delay | Blocker | Owner |
|---|---|---|---|---|---|---|---|
| Western Digital | WDC-8790 Clamp Ring Fixture | 06 Aug 2026 | 17 Aug 2026 | +11 days | Rework | Nurul Aziz | |
| Bosch Power Tools | BPT-4390 Stator Lamination Die | 07 Aug 2026 | 18 Aug 2026 | +11 days | Vendor ETA | Ravi Kumar | |
| Osram Opto | OSR-8960-A Optic Cavity Block | 10 Aug 2026 | 19 Aug 2026 | +9 days | Material | Siti Rahmah | |
| Ansell Malaysia | ANS-3280-B Chain Guide Rail | 11 Aug 2026 | 20 Aug 2026 | +9 days | Production Delay | Faizal Rahim | |
| Flextronics Penang | FLX-6501 Housing Trim Die | 05 Aug 2026 | 13 Aug 2026 | +8 days | Material | Tan Choon Hock | |
| Carsem Semiconductor | CSM-2150-A Pick Head Nozzle Plate | 06 Aug 2026 | 14 Aug 2026 | +8 days | Production Delay | Faizal Rahim | |
| Dyson Manufacturing | DYS-1050-C Shroud Core Insert | 07 Aug 2026 | 15 Aug 2026 | +8 days | Special Process | Lim Wei Sheng | |
| Kobe Precision | KBP-5430 Feed Cam Plate | 10 Aug 2026 | 14 Aug 2026 | +4 days | Engineering | Tan Choon Hock | |
| Carsem Semiconductor | CSM-2210-A Lead Frame Punch | 13 Aug 2026 | 13 Aug 2026 | — | Material | Lim Wei Sheng | |
| Dyson Manufacturing | DYS-1120-C Impeller Core Insert | 14 Aug 2026 | 14 Aug 2026 | — | Special Process | Siti Rahmah |